CompTIA Project+ Performance-Based Questions

6 free, original PBQs for Project+ (PK0-005), with drag-and-drop. Do each task, check it, and read why the answer is right.

Last updated

CompTIA Project+

6 performance-based questions

You do each task instead of picking an answer. Every question is explained after you check it, and you get a score at the end.

  1. 1Put the project phases in orderOrdering · Project Life Cycle Phases
  2. 2Sort the practices: Agile or WaterfallSorting · Project Management Concepts
  3. 3Put the change control process in orderOrdering · Project Management Concepts
  4. 4Name the risk responseMatching · Project Management Concepts
  5. 5Match the project documents and chartsMatching · Tools and Documentation
  6. 6Classify the data a project handlesMatching · Basics of IT and Governance

Take it further in OpenpassAI

Performance-based questions in every practice session

OpenpassAI’s practice sessions add performance-based questions, with command-line and network topology tasks, to full timed exams, AI explanations and a readiness score.

The questions

The Project+ performance-based questions on this page

Each one with its scenario and task. Try it above first, then open the explanation.

  1. Question 1 · Ordering · Project Life Cycle Phases

    Put the project phases in order

    A company has decided to replace its help desk software, and you’ve been named project manager. Your sponsor asks what happens when.

    Arrange the five phases from first to last.

    Show the explanation

    Discovery tests whether the idea is worth pursuing, usually with a business case. Initiating authorizes the project with a charter and identifies the stakeholders. Planning works out the scope, the schedule, the budget and the risks. Executing does the work, with progress monitored and changes controlled along the way. Closing hands over the result, releases the team and records the lessons learned.

  2. Question 2 · Sorting · Project Management Concepts

    Sort the practices: Agile or Waterfall

    Two teams in the same company run projects very differently. A new project coordinator is trying to work out which practices belong to which approach.

    Put each practice under the approach it belongs to.

    Show the explanation

    Waterfall is predictive: the requirements are settled first, each phase is completed before the next starts, and changes go through formal control. Agile is adaptive: work is delivered in short iterations, the backlog is reprioritized as needs change, and the team inspects its own way of working in regular retrospectives. Waterfall suits work with fixed, well-understood requirements; Agile suits work where they are expected to change.

  3. Question 3 · Ordering · Project Management Concepts

    Put the change control process in order

    Halfway through the project, the head of support asks for an extra report in the new software. It wasn’t in the agreed scope, and the request has to go through change control.

    Arrange the seven steps from first to last.

    Show the explanation

    A change starts as a written request and is logged, so nothing is agreed in a corridor. Its impact on scope, schedule and cost is assessed before anyone decides, because the decision depends on that impact. The change control board approves or rejects it. Only an approved change updates the plan and is implemented. Finally the change is checked and the stakeholders are told the outcome.

  4. Question 4 · Matching · Project Management Concepts

    Name the risk response

    The risk workshop produced five decisions, and each one needs the name of its response strategy in the risk register.

    Match each decision to the risk response.

    Show the explanation

    Transferring a risk passes its financial impact to another party, such as an insurer. Avoiding it changes the plan so the risk can’t happen. Mitigating it reduces its likelihood or its impact. Accepting it means taking no action in advance, often with a contingency reserve set aside. Exploiting is a response to a positive risk: acting to make sure an opportunity is realized. Sharing an opportunity with a partner is another positive response.

  5. Question 5 · Matching · Tools and Documentation

    Match the project documents and charts

    A stakeholder keeps asking where to find things, and each answer is a different project document.

    Match each description to the document or chart.

    Show the explanation

    The project charter authorizes the project and names its manager. The work breakdown structure divides the scope into deliverables small enough to estimate. A Gantt chart shows tasks as bars on a timeline, with their dependencies. A RACI matrix records who is responsible, accountable, consulted and informed for each task. The risk register lists each risk with its owner and response, and a burndown chart shows the work left in a sprint.

  6. Question 6 · Matching · Basics of IT and Governance

    Classify the data a project handles

    The project will move records between systems, and the compliance officer wants every data set labelled before the migration is planned.

    Match each data set to its classification.

    Show the explanation

    Personally identifiable information identifies a living person. Protected health information is health data linked to a person, and has its own rules. Payment card data falls under the card industry’s security standard. Intellectual property is what gives the company its commercial edge, and public data may be shared freely. The label decides how each data set must be handled in the project: who may see it, where it may be stored and whether it must be encrypted.

On the real Project+ exam

CompTIA lists Project+ among its certifications with simulation performance-based questions: tasks in an approximation of a real tool, such as a firewall, a network diagram or a terminal window. CompTIA’s page on performance-based questions, read on November 12, 2026.

Guide

How to practice performance-based questions

What a performance-based question is

CompTIA describes performance-based questions as exam items that test your ability to solve problems in real-world settings. Most are simulations: an approximation of a tool such as a firewall, a network diagram, a terminal window or an operating system.

You don’t pick an answer. You do the task, and there can be more than one correct way to do it.

Do the task before you read

Try each question cold. Getting it wrong first and then reading why teaches more than reading the answer and nodding along.

Read the explanation even when you’re right

A right answer reached by guessing is a wrong answer waiting for exam day. Every question here explains why each part is what it is.

Manage your time on exam day

CompTIA says a simulation question can be skipped and returned to later, with your work saved. If one is eating your time, move on, answer the multiple-choice questions and come back.

FAQs

Got Questions? We’ve Got Answers.

Find quick answers or contact our support team.

Does the real Project+ exam have performance-based questions?

Yes. CompTIA lists Project+ among its certifications with simulation performance-based questions: tasks in an approximation of a real tool, such as a firewall, a network diagram or a terminal window. That is from CompTIA’s page on performance-based questions, read on November 12, 2026.

Are these real exam questions?

No. They’re original tasks written to each exam’s published objectives. Using leaked real exam questions breaks every vendor’s exam rules.

How are performance-based questions scored on the real exam?

CompTIA says a performance-based question can have more than one correct way through it, that its scoring allows for the different approaches, and that partial credit may be given. Here, each question is scored by its parts, so you can see which part you missed.

Can I skip a performance-based question and come back to it?

CompTIA says a simulation question can be skipped and returned to later, and that your work on it is saved when you move on. A virtual-environment question has to be completed when you reach it: a warning screen tells you so first.

Do I need an account?

No. The questions run in your browser and nothing is saved. Sign up only if you want full practice exams and progress tracking.

Ready to Get Certified Faster?

Start free today or see it in action first.

OpenpassAI

Hi 👋 I’m OpenpassAI. Ready to prepare for your exam the smarter way?

Ready to explore OpenpassAI? I can show you how the platform helps you prepare, practice, and pass.